Warnervale, NSW

Warnervale Subdivision

54-lot residential subdivision · Under construction

Location
Warnervale, NSW
Client
Atlas Property
Contract value
$4.8 million
Commencement
July 2026
Target completion
March 2027
Status
Under construction
Aerial overview of bulk earthworks in progress at the Warnervale subdivision.

Scope of works

  • 54 residential lots
  • 7,000 m³ of bulk earthworks
  • 4,000 m² of asphalt pavement
  • 600 m² of rock and concrete sleeper retaining walls
  • 1,540 m² of footpaths
  • Sewer, electrical, water and NBN reticulation
  • 1.6 km of stormwater and subsoil drainage
  • On-site detention (OSD) basin
  • Existing road upgrades under Section 138
  • Soft landscaping with hardscape elements

Project overview

CBEM Constructions is delivering subdivision civil works for a 54-lot residential development in Warnervale, NSW, for Atlas Property. The $4.8 million project commenced in July 2026, with completion targeted for March 2027.

The scope brings together 7,000 m³ of bulk earthworks, 4,000 m² of asphalt pavement, 1,540 m² of footpaths and 600 m² of rock and concrete sleeper retaining walls. The utility package includes sewer, electrical, water and NBN reticulation, together with 1.6 km of stormwater and subsoil drainage.

Existing road upgrades under Section 138, soft landscaping with hardscape elements and an on-site detention (OSD) basin form part of the subdivision works. The construction photographs document bulk earthworks, subgrade ripping and recompaction, and rock excavation for the sewer trench; they are progress photographs rather than completed-project images.

Read about CBEM’s subdivision construction services, bulk earthworks, stormwater drainage and OSD systems and sewer and water infrastructure, or contact CBEM.

Earthworks in progress

The project includes 7,000 m³ of bulk earthworks. Progress photographs show site earthworks, subgrade ripping and recompaction.

Utilities & drainage

The scope includes sewer, electrical, water and NBN reticulation, 1.6 km of stormwater and subsoil drainage, and an OSD basin. Rock excavation for the sewer trench is shown in the project photographs.

Roads & finishing works

The project package includes asphalt pavement, footpaths, retaining walls, road upgrades and landscaping. Overall completion is targeted for March 2027.